How Long Does a Building Permit Take? We Timed 99,540 GTA Permits

The real end to end wait for a GTA building permit, computed from 99,540 city permit records, and why the law's 10 business days is a different clock.

Facts last verified

More about Toronto
Construction work in progress on an unfinished house with wooden framing

Key takeaways

  • For permits issued January 2024 to August 2026, the median recorded wait on a new detached house was 50 calendar days in Toronto (n=1,340), 173 days in Mississauga (n=294) and 62 days in Burlington (n=130).
  • A house interior alteration is far quicker: a median of 7 days in Toronto (n=3,270), 20 days in Burlington (n=651) and 35 days in Mississauga (n=3,264).
  • The Ontario Building Code period is 10 business days for a house, and it measures the first decision on a complete application, not the applicant's wait from filing to permit.
  • Bill 109's late decision fee refunds never covered building permits, and they were repealed on June 6, 2024 by Bill 185.
  • Of Toronto applications filed in 2019, 94.5 per cent had produced a permit by August 26, 2026, against 83.3 per cent of those filed in 2024.

Ontario law gives a city 10 business days to decide on a complete house permit application. The whole wait is another matter. Toronto's median new detached house permit took 50 calendar days, from the day the City logged the file to the day the permit came out. Mississauga's took 173. Burlington's, 62. Those are two different clocks, and that is the point of this piece. We timed 99,540 permits issued in three GTA cities between January 2024 and August 2026.

How long a permit really takes, city by city

Median means half the permits came out faster and half took longer. The n is how many permits sit behind each figure. Every number counts calendar days from the application date the city recorded to the issue date on that file.

Project

Toronto

Mississauga

Burlington

New detached house

50 days (n=1,340)

173 days (n=294)

62 days (n=130)

Addition to a house

45 days (n=873)

85 days (n=387)

52 days (n=276)

Interior alteration or renovation

7 days (n=3,270)

35 days (n=3,264)

20 days (n=651)

Deck

7 days (n=618)

not coded separately

30 days (n=177)

Second unit in a house

8 days (n=869)

50 days (n=1,731)

64 days (n=174)

Every permit type combined

29 days (n=85,398)

33 days (n=10,753)

27 days (n=3,389)

Only three cities publish an application date: Toronto, Mississauga and Burlington. Oakville's permit layer carries an issue date and no application date at all, and Brampton publishes permit records with issue side fields only. Neither can be timed, and neither is slow or fast here. There is nothing to measure.

A median hides the tail. A quarter of Toronto's new detached house permits came out within 29 days; a quarter took more than 99, and one in ten more than 258.

Two caveats travel with the table. Toronto's field records the day a file was "received and entered". Mississauga's metadata calls its field "the date the application was accepted", which lands after a prescreen (a first check that a file is complete). Those may not be the same moment, so read the gap between the two cities as rough. Burlington publishes no definition of its "In Date" field, on the layer, in its metadata or on its portal. We read it as the intake date because it precedes the issue date on 4,728 of 4,729 files. That reading is ours.

The two clocks, and why they never line up

Almost every page about permit timing mixes up two clocks.

The review clock is the legal one. It starts the day after you file a complete application. It stops when the city issues your permit or refuses it in writing. Complete means the form is filled in and signed, the drawings are in, the fees are paid, and you have declared in writing that the work breaks no other law.

The recorded wait is what the table counts. It starts the day the city logs your file, complete or not. It ends the day the permit is issued. It holds intake, every day the file sat incomplete, every round of corrections, and your own time answering them.

A 50 day recorded wait and a 10 business day review clock can both be true of one file. No GTA open dataset records the day a file became complete, or the day the first reviewer comment went out. So nothing here can say whether a city met its legal period.

What the law actually promises

The periods live in the Ontario Building Code, Division C, Article 1.3.1.3 and Table 1.3.1.3. Four classes:

  • a house where no dwelling unit sits above another, or a detached structure serving it up to 55 square metres: 10 days
  • a small Part 9 building: 15 days
  • a large Part 3 building: 20 days
  • a post disaster or high building: 30 days

Almost every homeowner job is the first row. A second unit with one dwelling above another is the exception: it sits in the 15 day row, and Mississauga publishes 15 business days for second unit applications. Toronto's House Stream still promises 10 business days for a house of up to two units.

Four of the five cities and towns here publish a 10 business day first review for house scale work. Toronto and Mississauga tie it to a complete application. Brampton attaches its 10 business days to its Standard Permit Application Service, available for all home renovation projects, with no completeness condition at all. Burlington publishes its periods in a council report rather than on its permit pages, and Oakville publishes no number of its own.

The Code writes "10 days", not "10 business days". Sentence 1.3.1.3.(8) is what turns them into business days: they "shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open". Sundays fall under that last phrase. Each city counts its own closed days, so two cities can reach different deadlines from one filing date.

The clock also ends at a decision, not at a permit.

Housekeeping: the current Building Code is O. Reg. 163/24, in force January 1, 2025; it revoked O. Reg. 332/12. Toronto's own complaints page still reprints the table from the revoked rule, though the day figures did not change.

The late permit refund that does not exist

Some pages promise a fee refund when a city misses its deadline. That is wrong twice over.

Bill 109 (More Homes for Everyone Act, 2022) did create rising fee refunds for late decisions. They went into the Planning Act, for zoning by-law amendments and site plan control, and into section 114 of the City of Toronto Act. Those are planning approvals. Nothing in Bill 109 touched the Building Code Act or the Building Code, so no permit fee was ever covered. Bill 185 (Cutting Red Tape to Build More Homes Act, 2024) repealed the refunds on June 6, 2024, leaving only transition wording for files received before that date.

So the Building Code Act holds no penalty, no automatic approval and no refund for a slow review. Toronto's own refund section, § 363-4.11 of Municipal Code Chapter 363, pays out when a file is withdrawn, cancelled or abandoned, or a permit is revoked. Lateness is not on the list. Toronto offers an appeal instead: "If you have a dispute about the time frames not being met. You may appeal to the Building Code Commission".

Why the recorded wait runs past the review clock

Toronto's by-law shows the mechanism in one sentence. Under Municipal Code § 363-3.2, a file sent in without a Zoning Applicable Law Certificate (the City sign off that your plans obey zoning) is "deemed by the Chief Building Official to be incomplete such that the periods within which a building permit shall be issued or refused ... will not apply".

Toronto's permit stream page puts it plainly: "Applications where no Zoning Applicable Law Certificate has been issued for the project are considered incomplete. There is no time frame for review of incomplete permit applications".

Zoning review therefore sits before the review clock starts, and so does most of the back and forth. Mississauga says so outright: "There is no guaranteed review time for resubmissions ... Each resubmission cycle could add two or more weeks". Burlington's building department told its council the same in report BB-05-24: "Subsequent resubmissions do not have stipulated legislated timelines in the OBC".

One study does test the review clock: Toronto auditing itself. In February 2024 the Auditor General reviewed 58 permit files. Of the 27 that were complete, 17 (63 per cent) did not meet the legal time frames, by 1 to 52 business days. Toronto Building's own budget notes had reported 89 per cent compliance for 2022. Intake alone took over two business days on more than 38 per cent of about 236,000 files, which is time before the review clock starts. The Auditor General adds that "the reasons for delays are not tracked". That is a finding about 58 files, not a verdict on the whole city.

What has changed since 2019

Toronto's small permits got much faster, and they have stayed faster.

Toronto median wait

2019

2022

2023

2024

2025

2026 to Aug

House interior alteration

12 days

20 days

16 days

6 days

7 days

6 days

Deck

40 days

55 days

36 days

7 days

8 days

6 days

New detached house

48 days

66 days

70 days

56 days

47 days

42 days

Each cell rests on 190 to 1,278 permits.

We checked whether the drop was a quirk of grouping. It is not: the same break shows up when permits are grouped by the quarter they were applied for. What caused it is not in the data, and no City page we read announces a change.

Mississauga moved the other way on new houses.

Mississauga median wait

2019

2022

2023

2024

2025

2026 to Jul

New detached dwelling

71 days

119 days

122 days

185 days

149 days

213 days

House alteration

29 days

47 days

35 days

32 days

35 days

43 days

Each cell rests on 59 to 1,398 permits.

Each city is compared only with itself in these two tables, so the wording caveat above does not touch them.

The files that never became permits

A median only sees permits that were issued. It cannot see a file still sitting, or one that ended with no permit. So we counted forward from the application instead, using Toronto's cleared and active permit extracts together.

Of Toronto applications filed in 2019, 94.5 per cent had produced a permit by August 26, 2026. Of those filed in 2024, 83.3 per cent had. The share recorded as Cancelled rose from 6.1 to 14.0 per cent. Decks are the sharpest case: 12.4 per cent of 2019 deck files ended Cancelled, against 49.1 per cent of the 379 filed in 2024.

The 2024 and 2025 groups are still open, so their issued share can only rise. Toronto publishes no definition of the Cancelled status, and the data cannot show which files an applicant dropped and which the City closed. We are not claiming that half of Toronto's 2024 deck applicants gave up.

On August 26, 2026 Toronto had 13,438 files with no issue date in a live review status, 7,710 of them over a year old. That count leaves out anything cancelled, refused, withdrawn or abandoned.

Six months of silence can end your file

Toronto Municipal Code § 363-3.12 says a file that "remains inactive or incomplete for six months after it is made ... may be deemed by the Chief Building Official to have been abandoned without notice". No letter has to be sent first. If your file is waiting on your own drawings, keep it moving.

How to keep your file out of the slow half

Most of the recorded wait happens before the review clock starts, which is where you have leverage.

  1. Get the zoning sign off first. In Toronto an issued Zoning Applicable Law Certificate is part of what makes a file complete. File without one and there is no review period at all.
  2. Send a complete package. Toronto's House Stream list is six items: the completed form, the owner's or agent's signature, one set of plans and specifications, an issued Zoning Applicable Law Certificate (ZAP), proof that applicable law is met, and all fees paid.
  3. Answer comments quickly. Nothing in the Code sets a deadline for reviewing a resubmission, and Mississauga puts a price on each round: two or more weeks.
  4. Check for a fast lane. Toronto Building aims to review Express Services jobs (small residential and commercial projects, solar panels, sign permits) "within 3 business days after the permit has been taken in".
  5. Watch the file. Toronto runs a public status lookup, updated as of the previous business day.

Mississauga is blunt about the part you control: total time "will vary depending on the quality of the submission and how responsive you are as an applicant".

Frequently asked questions

How long does it take to get a building permit in Toronto?

It depends on the job. On permits issued January 2024 to August 2026, Toronto's median ran from 7 days for an interior alteration (n=3,270) to 50 days for a new detached house (n=1,340). Both are whole file waits, not the review clock.

How long does it take to get a building permit in Ontario?

The law sets a review period, not your total wait. For a house it is 10 business days, and it runs only once your file is complete. Ontario publishes no province-wide figure for the real wait.

How long does a building permit take in Mississauga?

On permits issued January 2024 to July 2026, Mississauga's median ran from 35 days for a house alteration (n=3,264) to 173 days for a new detached dwelling (n=294). The City also publishes a 7 to 10 business day prescreen, then a first review of 10 business days.

How do I check my building permit status in Toronto?

Toronto runs a public Building Permit Application and Inspection Status lookup and publishes what each status word means. "Under Review" means "An Application has been accepted and the Review has started but is not completed". The data runs a business day behind.

What happens if the city takes longer than the legislated period?

Nothing happens by itself. There is no penalty, no automatic approval and no fee refund in the Building Code Act for a slow review. Toronto's published remedy is an appeal to the Building Code Commission.

Can I start work while I wait for the permit?

No. The province says you must get a building permit before you construct a new building over ten square metres, renovate or repair, add to a building, change its use, or dig or build a foundation.

Why did my neighbour's permit come out in a week and mine has not?

Project class explains most of it. In Toronto 81 per cent of house interior alterations were issued within 10 business days of the recorded application date, against 2 per cent of new detached houses. That is the gap between the two clocks, not a measure of whether the City met its legal period, which starts only once a file is complete. A file with no Zoning Applicable Law Certificate counts as incomplete, and the City sets no time frame for those.

Sources

  1. Building Permits: Cleared Permits (since 2017) · City of Toronto Open Data (retrieved )
  2. Building Permits: Active Permits · City of Toronto Open Data (retrieved )
  3. Building Permits (issued since January 1, 2018) · City of Mississauga Open Data (retrieved )
  4. Issued Building Permits layer, ISO attribute definitions · City of Mississauga (retrieved )
  5. Building Permits (Permit Building layer, issued and final only) · City of Burlington Open Data (retrieved )
  6. COB Permits MapServer layer 1, field aliases · City of Burlington (retrieved )
  7. PD Permits MapServer layer 13, field list · Town of Oakville (retrieved )
  8. Building Permits · City of Brampton GeoHub (retrieved )
  9. Building Permit Review Streams · City of Toronto (retrieved )
  10. Building permit cost and time frames · City of Mississauga (retrieved )
  11. Building: Homeowners and Residential Contractors · City of Brampton (retrieved )
  12. Building Permit Application Process · Town of Oakville (retrieved )
  13. Report BB-05-24: Resubmission of Building Permits · City of Burlington, Building Department (retrieved )
  14. Toronto Municipal Code Chapter 363, Building Construction and Demolition · City of Toronto (retrieved )
  15. Toronto Building Division: Audit of Intake and Plan Review of Applications for Building Permits · Auditor General, City of Toronto (retrieved )
  16. Ontario Amendments to the National Building Code of Canada 2020, dated July 17, 2026 · Ministry of Municipal Affairs and Housing (retrieved )
  17. O. Reg. 163/24: Building Code · Government of Ontario (e-Laws) (retrieved )
  18. O. Reg. 332/12: Building Code (revoked) · Government of Ontario (e-Laws) (retrieved )
  19. Building Code Act, 1992 · Government of Ontario (e-Laws) (retrieved )
  20. Planning Act, R.S.O. 1990, c. P.13 · Government of Ontario (e-Laws) (retrieved )
  21. City of Toronto Act, 2006 · Government of Ontario (e-Laws) (retrieved )
  22. Citizen's guide to land use planning: Building permits · Government of Ontario (retrieved )
  23. Toronto Building: Complaints and Compliments · City of Toronto (retrieved )
  24. Building Permit Application and Inspection Status · City of Toronto (retrieved )

How this guide was made

Computed on August 27, 2026 from the open permit extracts of Toronto, Mississauga, Burlington, Oakville and Brampton downloaded on August 26, 2026, then checked against the published review standards of five GTA municipalities, the Ontario Building Code timelines table, the Building Code Act, the Planning Act, the City of Toronto Act, Toronto Municipal Code Chapter 363 and the Auditor General of Toronto's February 2024 audit of building permit intake and plan review.

David BrownDB

Written by

David Brown

Editor & main author

David Brown is the editor of GTA Guide. He writes about the practical side of living in the Greater Toronto Area: what things cost, who to call, and what is worth your weekend. More about David Brown

Also worth reading

More in Permits & bylaws

All Permits & bylaws

See also